   Summary of Cornell Projects for 2013 and beyond
« No topic | Next topic »
Pages: 1 ... 3 4 5 6  Reply Reply Notify of replies Notify of replies Send Topic Send Topic Print Print
   Author  Topic: Summary of Cornell Projects for 2013 and beyond  (Read 34596 times)
SteveH
Registered Village Donor
Supreme Villager
*****





   


Gender: male
Posts: 1840
Re: Summary of Cornell Projects for 2010 and beyon
« Reply #60 on: Feb 5th, 2013, 10:49am »
Quote Quote Modify Modify

on Feb 5th, 2013, 10:22am, Cinderella wrote:
Does anyone know what is planned for the open field across from the Yee Hong Centre - south side of White's Hill in between Bur Oak and Walkerville.

 
It is owned by the catholic church but they have already come out and said the property is too small for a church.  So eventually it will be sold but that will likely be many years from now.  
 
The Cornell Secondary plan does have a provision for condos/retail for that property.
IP Logged
SteveH
Registered Village Donor
Supreme Villager
*****





   


Gender: male
Posts: 1840
Re: Summary of Cornell Projects for 2010 and beyon
« Reply #61 on: Feb 5th, 2013, 11:44am »
Quote Quote Modify Modify

The Secondary plan shows two options for the Catholic Church lands (SW of Whites Hill & Bur Oak). The first option is all the lands are used for a church. The 2nd option is the west half is used for a church and the East half used for Retail/residential. See page 61.
 
http://www.markham.ca/NR/rdonlyres/4A41B466-466E-4976-BA29-B50E5F321145/ 0/cornell_apr07.pdf
 
The lands north of Yee Hong are designated for Residential.
 
Either way nothing has been planned for these sites.
 
 
« Last Edit: Feb 5th, 2013, 11:49am by SteveH » IP Logged
SteveH
Registered Village Donor
Supreme Villager
*****





   


Gender: male
Posts: 1840
Re: Summary of Cornell Projects for 2013 and beyon
« Reply #62 on: Apr 22nd, 2013, 4:08pm »
Quote Quote Modify Modify

Updated Multi-Use Pathway project with latest information.
 
Multi-Use Pathway
« Last Edit: Apr 22nd, 2013, 4:21pm by SteveH » IP Logged
Adam_W
Supreme Villager
*****



Cornell Resident since June 1998

   


Gender: male
Posts: 465
Re: Summary of Cornell Projects for 2013 and beyon
« Reply #63 on: Apr 24th, 2013, 8:52am »
Quote Quote Modify Modify

Re: The lands that Steve H mentions at SW Buroak & Whites Hill.  Both parcels of land are still full blocks on Registered Plans.  This means that prior to any further construction on these lands (other than uses the properties are already used for) will require applications to the City of Markham and the Committee of Adjustment.  With that said the public will have a chance to put forward some input into a developers proposed revisions for the land use, and proposed zoning/subdivision of the lands.
Notifications of the impending changes would be sent out to land owners within a radius (300 metres) and signage erected on the properties regarding the nature of the proposed change and public meeting dates and written submission info.
If your interested keep your eyes open for the big white and yellow signs.  
IP Logged
indigo
Outstanding Villager
****





   


Gender: female
Posts: 163
Re: Summary of Cornell Projects for 2010 and beyon
« Reply #64 on: Oct 6th, 2014, 9:26pm »
Quote Quote Modify Modify

on Jan 21st, 2013, 12:31pm, mbds wrote:
So let's see...we've lived here for over 15 years now, and still no local grocery store, restaurants, cafes or other shops & services beyond the plethora of nail salons & physio places.  
Delayed indefinitely!
Methinks I'll be in a retirement home or pushing up daisies before these developers complete the live-play-work-shop-within-walking-distance of the Cornell vision.
Discouraging.

 
I hear you. Huh
 
I posted a thread asking if we will be getting in a 24/7 grocery store to see if anyone knows.  
 
But to your point, even just a grocery store would be good - Seems long overdue!
 
~~~~~~~~
I originally posted it in general but then moved it to this forum thinking it was more suitable here.
 
But now I see how little traffic is in this forum, I may move it back.
~~~~~~~~~~
 
On the up side, apparently there is a new bakery and coffee shop (with ltd hours):
 
http://www.cornellvillage.ca/cgi-bin/yabb/YaBB.pl?board=AllCornellDevelo pers;action=display;num=1410034198
« Last Edit: Oct 6th, 2014, 9:28pm by indigo » IP Logged
SteveH
Registered Village Donor
Supreme Villager
*****





   


Gender: male
Posts: 1840
Re: Summary of Cornell Projects for 2013 and beyon
« Reply #65 on: Jan 24th, 2015, 11:53am »
Quote Quote Modify Modify

Here is the latest on the Multi-use Pathway.
 
http://www2.markham.ca/markham/ccbs/indexfile/Agendas/2015/Development%2 0Services/pl150127/MUP%20Revised%20DSC%20Presentation%20Jan%2027,%202015.pdf
 
For those not familiar with the eastern portion of this Pathway here is an update on the Bob Hunter Memorial Park (14th ave and Reesor Rd - next to Box Grove) that is also a part of Rouge Park. Most of these trails already exist with the remainder to be completed in 2015.
 
http://www2.markham.ca/markham/ccbs/indexfile/Agendas/2014/Development%2 0Services/pl140610/Cedarena%20Permit%20Presentation.pdf
« Last Edit: Jan 24th, 2015, 12:18pm by SteveH » IP Logged
SteveH
Registered Village Donor
Supreme Villager
*****





   


Gender: male
Posts: 1840
Re: Summary of Cornell Projects for 2013 and beyon
« Reply #66 on: Jun 25th, 2015, 12:41am »
Quote Quote Modify Modify

I have updated the central park and transit terminal projects with the latest information.  It looks like the lease for the grocery store fell through so I have updated the Lindvest project to Delayed.
IP Logged
bartimus
Outstanding Villager
****





   


Posts: 102
Re: Summary of Cornell Projects for 2013 and beyon
« Reply #67 on: Jun 25th, 2015, 9:59am »
Quote Quote Modify Modify

on Jun 25th, 2015, 12:41am, SteveH wrote:
I have updated the central park and transit terminal projects with the latest information. It looks like the lease for the grocery store fell through so I have updated the Lindvest project to Delayed.

 
Is that in regards to the 'Cornell Woods' plaza? Does that mean that whole development will be delayed?
« Last Edit: Jun 25th, 2015, 10:00am by bartimus » IP Logged
SteveH
Registered Village Donor
Supreme Villager
*****





   


Gender: male
Posts: 1840
Re: Summary of Cornell Projects for 2013 and beyon
« Reply #68 on: Jun 25th, 2015, 12:28pm »
Quote Quote Modify Modify

on Jun 25th, 2015, 9:59am, bartimus wrote:

 
Is that in regards to the 'Cornell Woods' plaza? Does that mean that whole development will be delayed?

 
Yes, this relates to Cornell Woods.  Any commercial development needs a lead tenant and for Lindvest they have always stated they needed a grocery store to sign up before they would build anything.
IP Logged
Adam_W
Supreme Villager
*****



Cornell Resident since June 1998

   


Gender: male
Posts: 465
Re: Summary of Cornell Projects for 2013 and beyon
« Reply #69 on: Jun 26th, 2015, 9:19am »
Quote Quote Modify Modify

Steve H, where do we find the updated (or original) Viva Terminal and Park status reports you mention above?
IP Logged
SteveH
Registered Village Donor
Supreme Villager
*****





   


Gender: male
Posts: 1840
Re: Summary of Cornell Projects for 2013 and beyon
« Reply #70 on: Jun 26th, 2015, 10:39am »
Quote Quote Modify Modify

on Jun 26th, 2015, 9:19am, Adam_W wrote:
Steve H, where do we find the updated (or original) Viva Terminal and Park status reports you mention above?

 
You can find the details in this presentation and minutes.
 
http://static1.1.sqspcdn.com/static/f/1262363/26219175/1431402161440/Col in-Campbell-CRA-AGM-Presentation-2015+.pdf?token=6iupsah34jwv9JM%2F6PtGlyHIZHM%3D
 
http://static1.1.sqspcdn.com/static/f/1262363/26219166/1432571825297/Cor nell_CRA+_2015_AGM_Minutes.pdf?token=6iupsah34jwv9JM%2F6PtGlyHIZHM%3D
 
 
IP Logged
EMC2
Villager
**



I love YaBB 1G - SP1!

   


Posts: 37
Re: Summary of Cornell Projects for 2013 and beyon
« Reply #71 on: Jul 10th, 2015, 1:38pm »
Quote Quote Modify Modify

Good to see that they are planning to build 4 lit tennis courts in the new Cornell Park.  There aren't too many tennis courts in close proximity to our area.  Hope that they will have a proper surface, and not of the black asphalt variety that chews up the balls!
IP Logged
bartimus
Outstanding Villager
****





   


Posts: 102
Re: Summary of Cornell Projects for 2013 and beyon
« Reply #72 on: Jul 10th, 2015, 2:06pm »
Quote Quote Modify Modify

on Jun 27th, 2015, 9:19pm, amiyum wrote:
Was the grocery store Sobeys? seems like they are going through a major restructuring
http://www.huffingtonpost.ca/2015/06/26/sobeys-to-eliminate-1300_n_76702 16.html?utm_hp_ref=canada-business&ir=Canada+Business

 
I remember hearing that Sobeys was the store, so it could be linked to their restructuring.
I wonder how hard it is to find grocery store that is interested. I figured they'd want to jump at such opportunity.
IP Logged
indigo
Outstanding Villager
****





   


Gender: female
Posts: 163
Re: Summary of Cornell Projects for 2013 and beyon
« Reply #73 on: Oct 5th, 2015, 6:57pm »
Quote Quote Modify Modify

Sobeys closed their 24 hour store on McGowan not long ago so I would say it is doubtful they would be opening another now.
 
I hope some 24 hour store opens nearby.
IP Logged
SteveH
Registered Village Donor
Supreme Villager
*****





   


Gender: male
Posts: 1840
Re: Summary of Cornell Projects for 2013 and beyon
« Reply #74 on: Jan 25th, 2016, 10:13pm »
Quote Quote Modify Modify

Here are few more details on the bus terminal from the 2016 York Region budget.
 
http://www.york.ca/wps/wcm/connect/yorkpublic/ff85ffdc-9b48-44fd-b548-3d 4132a59aea/nov+19+regional.pdf?MOD=AJPERES
 
 
- Cornell Terminal an 11-bay bus terminal located in the vicinity of MarkhamStouffville
hospital in the City of Markham
- Conceptual design and engineering work to commence in early 2016, and
construction work to start in the Fall
- Projected to be in service by end of 2017
« Last Edit: Jan 25th, 2016, 10:14pm by SteveH » IP Logged
Pages: 1 ... 3 4 5 6  Reply Reply Notify of replies Notify of replies Send Topic Send Topic Print Print

« No topic | Next topic »
Powered by YaBB 1 Gold - SP 1.3.1!
Forum software copyright 2000-2004 Yet another Bulletin Board